Background
In March of 2018, the Ministry of Education (EDU) provided capital funding approval to construct a new four (4) classroom addition to serve 92 pupil places at George Syme Community School. The addition is required to accommodate the increase in enrollment due to the grade range expansion of the Regular and French Immersion tracks to serve all grades to Grade 8.
Since the EDU approval of the business case, ³Ô¹ÏºÚÁÏÍø has completed the “Site Plan Approval Process” (SPA), detailed design of the project, received “Approval to Proceed to Tender” (ATP) from the Ministry of Education, obtained building permits from the City of Toronto, and tendered the construction to pre-qualified General Contractors.